The Kitsap County building permit process for homeowners, in short: confirm your project needs a permit, submit complete plans to the Department of Community Development (DCD) through its Online Permit Center, pass the completeness check, answer any plan-review corrections, and collect your permit. Your place in DCD’s review queue counts from the date a complete application is accepted, so a complete first submittal is the biggest thing you control.
Washington’s SB 5290 set decision deadlines that took effect January 1, 2025 — 65 days for permits that don’t require public notice (Type 1) and 100–170 days for permits that do (Type 2 and above) — but those deadlines cover land-use and environmental permits such as shoreline permits and variances. Kitsap County’s own SB 5290 FAQ says building permits are not currently interpreted as being affected, so a home addition or remodel building permit has no statutory clock.
In practice, a typical addition or remodel permit moves through pre-application review, a completeness check, plan review, and (for larger projects) public notice before approval. Understanding this sequence — and where design decisions can speed it up or slow it down — is the difference between a permit that sails through and one that stalls for months.
Silverdale is unincorporated, so projects there are permitted by Kitsap County DCD through this same process. See our Silverdale architecture and interior design services.
Before the process starts, check whether your project needs a permit at all. These rules come from DCD’s “Do I Need a Building Permit?” guide for unincorporated Kitsap County:
Even without a building permit, you may still need a plumbing, electrical or mechanical permit, and the work must still meet building codes, zoning setbacks and shoreline rules. Poulsbo, Bainbridge Island, Bremerton and Port Orchard run their own permit offices, so these county rules apply only outside those cities. On the island, follow our guide to the Bainbridge Island building permit process instead. Planning a backyard cottage? Read our guide to Kitsap County ADU requirements first. Building in Bremerton? Talk to an architect in Bremerton who knows the city’s process.
Two homeowners can submit similar-looking additions and see very different timelines — the difference usually comes down to design decisions made before submittal, not luck. Projects that stay within existing setbacks, don’t touch critical areas (wetlands, steep slopes, shorelines), and arrive with complete, code-compliant construction documents on the first pass move through review the fastest.
Projects that require variances, sit in a critical area, or need multiple resubmittals to fix incomplete plans routinely take longer, because each resubmittal sends the plans back through another round of review.
Once your application is accepted as complete, you can follow it on DCD’s Permit Timeframes & Statistics page: the “Where Is My Permit In Line?” dashboard shows your position in the review queue by permit number.
A licensed architect’s role in the Kitsap County permit process isn’t just producing drawings — it’s anticipating what DCD will flag before submittal. That means checking zoning and setback compliance, coordinating structural and energy-code documentation, and assembling a complete submittal package so the completeness review doesn’t bounce it back. For homeowners planning an addition, remodel, or new home in Kitsap County, this upfront coordination is usually what separates a permit that clears in the target window from one that drags through multiple review cycles. Buying land first? A feasibility study before you buy a home site surfaces these issues before you commit.
There is no statutory deadline for the building permit itself: Kitsap County’s SB 5290 FAQ says building permits are not currently interpreted as covered. The bill’s deadlines (65 days for Type 1, 100–170 days for Type 2 and larger permits requiring public notice) apply to land-use and environmental permits, such as shoreline permits and variances. Actual timelines depend heavily on how complete and code-compliant the initial submittal is.
Type 1 and Type 2 are land-use review types, not building-permit categories. Type 1 permits generally don’t require public notice and move through review faster (65-day statutory maximum under SB 5290). Type 2 and higher permits require a public notice and comment period, which extends the deadline to 100–170 days depending on the specific permit type. The building permit for an addition or remodel is reviewed separately and has no statutory deadline at present.
Yes, if the deck is attached to a building, is 30 inches or more above grade (18 inches on shoreline lots), is 200 square feet or more, serves as the main entry landing, or is near a critical area or buffer. A small, low, freestanding deck away from critical areas does not need one, but it must still meet setbacks and other county rules.
It’s not required for every project, but for additions, new construction, or anything touching a critical area, a pre-application meeting with Kitsap County DCD is strongly recommended — it surfaces zoning and site issues before they turn into a resubmittal during formal review.
SB 5290’s deadlines cover land-use and environmental permits, not the building permit itself, and their clock generally starts once an application is deemed complete — incomplete submittals, requests for additional information, and required resubmittals can add time outside that window. A complete, well-coordinated submittal on the first pass is the biggest factor in keeping either kind of review moving.
Yes. An architect familiar with Kitsap County’s requirements can identify zoning, setback, and code issues before submittal and assemble a complete documentation package, which reduces the resubmittal cycles that are the most common cause of permit delays.
Bluefoot Architecture & Design works with Kitsap County homeowners from early feasibility through permit documentation and management, coordinating the process so your project moves through DCD review as smoothly as possible. Contact us to talk through your project, or call 360-602-2965.